Sam Kong underpass road-surfacing finally begins

PHUKET: After more than a month of preparation work laying the foundations for the surface roads on the west side of the Sam Kong Underpass, workers today (July 22) began paving the road surface.

constructiontransporttechnologyweather
By Chanida Summast

Friday 22 July 2016, 05:46PM


Work to resurface the roads at the beleaguered construction site began on June 19, with statement of intent to complete the road surfacing within 20 days. (See story here.)

However, intermittent heavy downpours during the past month forced the workers to breach that deadline, Highways Department Project Engineer Chalermpol Wongkiettikun told The Phuket News today.

“At this stage, completing the roads above and around the Sam Kong Underpass will be finished around mid-August – if no more rain slows us down,” he said.

“Today workers started laying asphalt on the road in front of Aphrodite. If no rain affects work there, this section should be finished by next week. The resurfacing of the roads is progressing very slowly at that section due to the number of buses coming to Aphrodite.” he added.

“After we complete this section, we will resurface the road in front of Wat Sam Kong and then front of Thanachart Bank,” Mr Chalermpol said.

 

 

Comment on this story

* Please login to comment. If you do not have an account please register below by simply entering a username, password and email address. You can still leave your comment below at the same time.

Comments Here:
Comments Left:
# Characters
Username:
Password:
E-mail:
Security:

Rorii | 23 July 2016 - 12:17:36

KC.. is that the tunnel with the "shadow" that no-one is game enough to follow up on?

Whos In Charge? | 23 July 2016 - 10:57:06

Let's hope they put an asphalt overlay on top of the concrete , my dentures can't stand up to the shake rattle and roll much longer.....

Kurt | 23 July 2016 - 08:22:17

KCPhuket:..Not soon, I guess. First they have to finish the ceiling - and wall works, than all the 'real' lights.( still now emergency lights). After that the resurfacing?

I am sure many readers, if they live on Phuket, have noticed the very few numbers of workers there, day in day out.
The underpass is open since Songkran,( unfinished) as ordered by a visiting Minister.
Since then no...

KCPhuket | 23 July 2016 - 02:40:21

When they gonna resurface the crap concrete in the tunnel??

Have a news tip-off? Click here

 

Phuket community
Layan lockout: Public access denied amid Supreme Court wrangle for B10bn beachfront land

There is only one - same one who believes action against nominee sharleholders is incorrect. 60 mill...(Read More)


TAT praises visa-on-arrival fee waiver extension to April 30

It appears that TAT is accepting the reality that tourism numbers have dropped considerably over the...(Read More)


New B25mn tsunami-warning buoy ‘to be operational tomorrow’

From Oct 25, 2017 till today Jan, 17, 2019 there was that location no working tsunami buoy? Excused...(Read More)


Six houses destroyed by fire

Of course he knows them.Probably checks on them whenever he sees a car parking outside a shed on hi...(Read More)


Still no charges for taxi driver who wiped out six vehicles, killed motorcyclist

I'm fascinated by this comment "We need Insp K on the case!!" can you at least try and...(Read More)


Still no charges over deadly collision in Chalong that killed two tourists

"What this article is about is a motor accident. Get with the program. Even Australia as are ma...(Read More)


Korean tourists given rustic welcome as airport taxi hits cow

Of course the person to blame for the accident is the cow (which could be charged with damage to pro...(Read More)


Phuket in the cold as ’Smart Driver’s licences’ launch

Chief Banyat 'declines' a lot. Probably he has no clue, not informed, and is shocked himsel...(Read More)